Perform Backup and Recovery of Standalone Data Lake in SAP HANA Cloud

Learn to backup and recover the data in your standalone data lake in SAP HANA Cloud using a production account.

Overview

🎓 beginner 10 min. SAP HANA CloudBeginnerSAP HANA Cloud Data Lake

You will learn

  • โœ”The backup schedule for the database
  • โœ”What happens when there is a failure of a data lake instance
  • โœ”How is an instance recovered after failure
  • โœ”How to make a service request for recovery
Unknown U Unknown August 15, 2023
Created by June 3, 2021
Contributors

Prerequisites

Steps

Intro

The backup and recovery process of SAP HANA Cloud, data lake is managed by SAP itself, unlike what customers of SAP IQ are familiar with on premise. Let’s look at how this works.


Step 1 Introduction to database backups
โ€”

Data lake instances are automatically backed up at regular intervals to safeguard your database and ensure that it can be recovered fast.

Backups of data lake instances are stored in the object store of the corresponding infrastructure as-a-service (IaaS) provider. That means that instances on AWS are stored in Amazon S3 buckets, and those on Microsoft Azure are stored in the Azure blob store, for example.

All backups are encrypted using the capabilities of the IaaS provider and are replicated in additional availability zones in the same region. The default retention time is 14 days and can be increased or decreased.

Step 2 What is the database backup schedule?
+
Step 3 What happens if there is a failure?
+
Step 4 How to make a recovery?
+
Step 5 How to make a service request?
+
Step 6 Knowledge Check
+

Resources

Discussion

Share feedback on this tutorial or join the conversation in SAP Community.

Submit detailed feedback Discuss in Community
Steps
Step 1 of 6
1. Introduction to database backups 2. What is the database backup schedule? 3. What happens if there is a failure? 4. How to make a recovery? 5. How to make a service request? 6. Knowledge Check

Learn more →